Project Update - April 2017

Arrow Road Construction is scheduled to begin construction on April 19th.  Concrete and storm sewer work will take place first and include repairs to sidewalks, curbs, and inlets.  After this work is completed, roadway milling, pavement patching, and placement of a new asphalt surface will follow.  The project is scheduled to be completed by the end of June.